Commissioners appoint debris-monitoring contractor and order new debris-removal RFP
Summary
After a review panel recommended a top-ranked contractor for disaster debris monitoring, commissioners approved the monitoring contract required for FEMA reimbursement and voted to cancel and reissue the debris-removal RFP because the scope and permitting requirements were unclear.
Get email alerts on the Disaster Debris topic
No spam. Unsubscribe anytime.
The Lincoln County Board of Commissioners accepted a review panel's recommendation Feb. 25 to contract a monitoring firm for disaster debris work and separately voted to cancel and reissue the debris-removal solicitation because the original request did not clearly define scope or permitting.
A scoring tabulation presented to the board showed the top monitoring candidate scored roughly 96 points. Commissioners moved to appoint the recommended firm (named in the meeting motion as "Austin Solutions") to provide disaster debris monitoring services; the board approved the motion by voice vote.
Separately, the review committee told commissioners the debris-removal and disposal RFPs did not reflect the true scope of work and failed to address permitting questions. The committee recommended cancelling and reissuing the RFP after staff obtains clearer information on the extent of debris, what permitting agencies will allow, and whether a federal declaration will provide FEMA reimbursement.
Commissioners approved the recommendation to cancel and reissue the debris-removal RFP. The county explained that until it knows the status of a federal disaster declaration and permitting constraints, it cannot accurately price or scope large-scale removal. One commissioner noted that some piles may not be permissible to remove without specific permits and that leaving certain debris in waterways may be required by permitting agencies.
Next steps: The monitoring contractor will advise the county during the procurement process but will not draft the RFP. Staff will work with permitting agencies, affected property owners and the contractor to develop a clearer scope and then reissue the debris-removal solicitation.