Commission recommends preliminary/final plat for Eastwood Energy Center No. 4
Summary
Staff recommended and the commission recommended approval of a three-lot plat (Eastwood Energy Center No. 4) creating 8-, 4.4- and 6-acre lots for industrial development; conditions included drainage coordination, traffic-impact studies at building permit, easements for stormwater ponds, and potential wetland investigation.
Get email alerts on the Preliminary Final Plat topic
No spam. Unsubscribe anytime.
The Planning Commission voted to recommend approval of a combined preliminary and final plat to subdivide a previously recorded parcel into three industrial lots for the Eastwood Energy Center No. 4.
Britney Mitchell, representing city planning staff, said the proposal creates Lot 1 (8 acres), Lot 2 (4.4 acres) and Lot 3 (6 acres). Mitchell said Lot 1 and Lot 3 have concept build-outs and identified potential tenants, while Lot 2 currently does not have an identified tenant. "The developer wishes to create a 3 lot plat to create new building sites for 2 identified future tenants that meet the zoning requirements for use," Mitchell said.
Staff noted that stormwater will need to be handled on-site for each building and that a traffic study must be submitted at the time of building-permit application. Conditions recommended by staff included continued coordination with the city engineer on drainage and site design, submission of traffic-impact studies for each build-out, easements for stormwater pond areas and shared drives, connection-fee payments, and a wetlands investigation or notice demonstrating absence of wetlands.
Applicant project manager Nate Mira said two site designs are in progress for Lots 1 and 3 and confirmed Lot 2 currently has no identified tenant. A commissioner asked whether the on-site circulation shown near the pond was a road; Mira replied it was intended for semi-vehicle circulation on-site.
The commission moved and unanimously recommended approval; staff said anticipated council action is scheduled for June 8.