Coventry council reports $1.2M culvert funding, parks and bridge projects remain under review
Summary
Town Manager James Drumm said the State Bond Commission provided $1.2 million for Broadway culvert repair; other projects — a Coventry Village water tower, Patriots Park playscape, Parker Bridge redesign for fish passage and Daly Road engineering funding — remain open or on hold and require further design or funding.
Get email alerts on the Infrastructure Projects topic
No spam. Unsubscribe anytime.
Town Manager James Drumm told the Coventry Town Council on June 1 that the State Bond Commission provided $1.2 million to fund repairs to the Broadway culvert, a project first flagged after a 2020 washout revealed a deteriorated underground pipe.
Drumm said the temporary patch installed after the washout has held but the town sought permanent repairs. He described the bond allocation as intended to prevent future road closure in the event of another washout. The Coventry Village water tower project was also submitted to the Bond Commission but was not selected; Drumm said the project remains on a standby list for potential future Bond Commission meetings.
Drumm reported that contractors completed work on the Coventry High School HVAC project; bills have been approved by the School Building Committee and the Board of Education must certify minutes and provide or verify canceled checks before the town can submit documentation for state grant reimbursement and close the project by the end of June.
On Patriots Park improvements, Drumm said two playscape bids came in higher than expected and staff are working with the contractor to value-engineer the proposal. The park grant also funds geese deterrent measures; engineering and a recommendation from Dr. Kortmann proposed installing a water circulator and some fencing to reduce geese presence.
Drumm said the Parker Bridge (culvert) project is on hold while CT Fisheries conducts a study of upstream/downstream fish to determine whether the culvert design must be altered to allow fish passage, a change that would increase costs. Councilor Mark Wheaton raised the funding gap for Daly Road, noting engineering for this phase needs about $450,000; Drumm confirmed past attempts to set aside $200,000 per year for the project were not possible and the town will need to consider debt service or bonding for future phases.
Why it matters: these are capital projects that affect road safety, stormwater flow, recreation and school facilities; several items require additional approvals, design changes, or funding decisions that will affect the town's capital planning.
No formal votes on these projects were taken at the June 1 meeting; managers and councilors discussed next steps and scheduling for public hearings or future agenda items.