Council approves emergency repairs at water intake after generator and meters fail
Summary
A failing generator and two obsolete particle meters at the rainy collector required immediate expenditure; council approved a mid‑year budget amendment to cover diagnosis, repairs and replacements to keep the water system in compliance.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
City staff told the council that routine generator maintenance found oil‑in‑water and water‑in‑oil contamination in the 44‑year‑old rainy collector generator; repairs and parts replacement were estimated at roughly $29,000 plus diagnostic, SCADA integration and contingencies. Separately, two particle detectors used for turbidity/particle measurement failed or no longer talked reliably to SCADA, requiring purchase, calibration and integration estimated at about $19,000 plus SCADA work. The council approved a FY 2025–26 budget amendment (Resolution No. 2026‑45) to fund the immediate repairs and replacements so the plant can continue operations and remain in regulatory compliance.
Staff noted a full generator replacement would be substantially more expensive and not part of this short‑term action; the budget amendment was intended to keep operations stable and buy time for longer‑term planning.