Committee approves $20M renovation plan and purchase of BOA building; item goes to full commission

Rutherford County Budget Committee · June 4, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Budget committee voted 5–2 to proceed with purchase and renovation of the BOA building (purchase price included in total estimate), with staff reporting about $12.8M already set aside; final approval will be at full commission after this recommendation.

The Rutherford County Budget Committee voted to proceed with purchase and renovation of the Bank of America (BOA) building, advancing a plan that combines an $8 million purchase price with renovation estimates that put the total program near $20 million.

Architects from Klein Sweeney and pre-construction representatives from American Constructors presented updated cost estimates and a construction schedule that would begin demolition in late August and include an optional third floor as an alternate. Jacob Davis of Klein Sweeney said revised FF&E pricing and subcontractor feedback reduced some line items and that current planning includes demolition, construction documents and contingency for unknown conditions behind existing walls.

Why it matters: committee materials showed roughly $9.5 million already allocated for the project and another $3.3 million available from prior projects, so staff said roughly $12.8 million is set aside; the remainder would be funded from internal county reserves without new borrowing under staff’s stated plan.

What was said: Davis and American Constructors reviewed cost-control opportunities including reusing some electrical gear, alternate facade treatments and phased design choices. ‘‘The total cost down there at the bottom includes everything, including the $8 million building purchase,’’ Davis said; American Constructors noted multiple build options and scope adjustments to control costs.

The vote and next steps: the committee approved moving forward with the purchase by roll call (five in favor, two opposed). Staff said the committee’s approval will be reported under the budget committee report at the next full commission meeting for a standalone vote, and that the full commission can reverse the committee’s decision.

Actions: The committee’s vote sends the purchase and renovation proposal to the full commission for final action; staff will continue design development, subcontractor pricing and value-engineering to refine the budget.