Mitchell Field boat launch near completion; board delays grand opening until signage and final as-builts are complete

Harpswell Select Board · June 4, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Town staff reported the Mitchell Field boat launch and Potts Point town dock are close to completion but signage and final as‑built plans remain outstanding; the board agreed to wait to set a public opening and to pilot front‑gate access and a one‑way traffic pattern to manage initial demand.

Town staff told the Harpswell Select Board that the Mitchell Field boat launch is nearly ready for use but that signage remains the final outstanding item, so the board will delay any formal grand‑opening until signs and as‑built plans are in place.

Staff said crews have completed most construction work and that the contractor Wyman and Simpson will provide as‑built plans before the town releases final payment; a small $1,500 change order was added for hardware to keep the float from moving into the ramp. The board agreed to hold final payment pending receipt and review of as‑built plans.

Board and staff discussed traffic patterns for the launch and whether to open the front gate immediately. Staff recommended a pilot one‑way loop using Lower Meadow Road to the town launch and returning via Community Drive; they also recommended giving Mary Meeting Shellfish advance notice if the gate opens to allow that business to adjust operations. The board approved trying a limited pilot and said the gate could be reopened or closed later if problems arise.

The board also noted that the Potts Point town dock is nearing completion and may be ready in another week or two; small ribbon‑cutting events were suggested once final work and signage are complete.

Next steps: staff will require as‑built plans from Wyman and Simpson before releasing final payment, coordinate signage installation, and select an opening date once signage and any traffic‑management details are confirmed.