U.S. Forest Service outlines bridge bids, timber projects and hiring as part of recovery work
Summary
The U.S. Forest Service told commissioners two temporary highway‑loaded 'acro' bridges are going to bid May 13 to restore access, engineering on Lake Creek Bridge is being contracted, thinning and road‑work contracts are underway under Good Neighbor Authority, and the agency projects 56–60 million board feet of timber volume this year (including salvage).
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
A U.S. Forest Service representative updated Lincoln County commissioners on May 6 about recovery projects and ongoing work in the wake of recent floods and wildfire impacts.
The Forest Service said two temporary, highway‑rated 'acro' bridges (for heavy loads such as log trucks) are scheduled to be advertised for bid by May 13; those temporary crossings are intended to restore access quickly while permanent funding and design are pursued with Federal Highways over a longer timetable. The agency also said it was preparing to award an engineering assessment for the damaged Lake Creek Bridge.
Agency staff described active roadwork and fuels projects under the county’s priority list and under Good Neighbor Authority partnerships, including thinning crews funded in part by the National Forest Foundation. The Forest Service representative said several projects will start this season and that the agency anticipates roughly 56–60 million board feet of work across multiple sales this year, with five to seven projects accounting for new or added salvage volume.
Commissioners asked for a short public explanation of NEPA; the representative defined NEPA as the National Environmental Policy Act, the federal framework used to ensure environmental compliance on projects that require assessments or public comment.
Why it matters: restoring bridges and roads is critical for public safety, commercial access (especially timber hauling) and longer‑term reconstruction planning. Timber sales and salvage volumes affect local economies and contractor scheduling.
Next steps: temporary bridges to be bid in mid‑May; engineering work on Lake Creek Bridge to proceed with an awarded contract; Forest Service and state partners will continue to refine project schedules and public outreach as NEPA and litigation processes conclude on specific projects.