Airport project moved to 2025; master plan highlights growth goals
Summary
The commission approved moving a $580,043 pavement maintenance project from 2024 to spring 2025 because of contractor timing and paint-temperature requirements; the airport master plan prioritizes apron development and other long-term facility needs, with federal and state grants covering about 95% of planning costs.
Get email alerts on the Airport topic
No spam. Unsubscribe anytime.
Airport Director Anthony Dudas told the commission Oct. 22 that a pavement maintenance contractor could not begin work until Oct. 7 and that paint-application temperatures required delaying striping until spring; he asked the commission to move $580,043 in project spending from 2024 to 2025. Commissioners were told federal and state grants supporting the project will remain intact and the city's share is roughly $30,000 after reimbursements. The commission approved the budget-year adjustment by voice vote, 4-0.
Dudas also summarized the airport master plan (initiated in 2021) that guides 20 years of maintenance and development, noting goals for cargo-apron and commercial development, completed de-icing apron work, and facility recommendations including additional apron/aircraft parking, a maintenance building expansion, ground-service equipment storage and sanitary-sewer improvements. He said the plan is funded primarily by federal and state grants and helps prioritize investments and forecast capacity needs.