Airport project moved to 2025; master plan highlights growth goals

Board of City Commissioners, Williston, North Dakota · October 22, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The commission approved moving a $580,043 pavement maintenance project from 2024 to spring 2025 because of contractor timing and paint-temperature requirements; the airport master plan prioritizes apron development and other long-term facility needs, with federal and state grants covering about 95% of planning costs.

Airport Director Anthony Dudas told the commission Oct. 22 that a pavement maintenance contractor could not begin work until Oct. 7 and that paint-application temperatures required delaying striping until spring; he asked the commission to move $580,043 in project spending from 2024 to 2025. Commissioners were told federal and state grants supporting the project will remain intact and the city's share is roughly $30,000 after reimbursements. The commission approved the budget-year adjustment by voice vote, 4-0.

Dudas also summarized the airport master plan (initiated in 2021) that guides 20 years of maintenance and development, noting goals for cargo-apron and commercial development, completed de-icing apron work, and facility recommendations including additional apron/aircraft parking, a maintenance building expansion, ground-service equipment storage and sanitary-sewer improvements. He said the plan is funded primarily by federal and state grants and helps prioritize investments and forecast capacity needs.