Shepherdsville council approves $22.5 million assistance agreement to expand wastewater plant

Shepherdsville City Council · June 8, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Shepherdsville City Council voted June 8 to authorize an assistance agreement with the Kentucky Infrastructure Authority to secure up to $22,500,851 in loan funds for a wastewater treatment plant expansion (project A24-021S) intended to reduce stormwater-driven overflows and increase maintenance flexibility.

The Shepherdsville City Council approved a resolution June 8 authorizing an assistance agreement with the Kentucky Infrastructure Authority that makes up to $22,500,851 in loan funds available for project A24-021S, a planned expansion of the city's wastewater treatment plant.

Arthur, a city wastewater staffer who described the technical need for the project, said the plant currently has "a biological treatment capacity of 5.25 MGD" and that storm events push the system from "an average daily flow of 2,000,000 gallons to 10,000,000 gallons a day" at the treatment plant. "With this expansion, we will be able to have those storm events take place, and we will be able to sleep at night knowing that we are keeping everything within the pipe and everything getting treated so that our waterways stay clean and clear as they should," Arthur said. He listed project elements as two clarifiers, two sludge-holding tanks, a plant drain pump station and a new UV treatment unit and said the construction schedule targets substantial completion in April 2028.

Council members moved and seconded the resolution after Arthur's presentation. The roll-call-style voice vote recorded affirmative responses from the councilmembers present and the resolution was approved. The resolution text read at the meeting identifies the loan amount, the borrower (the city of Shepherdsville) and project number A24-021S and authorizes the mayor and city clerk to execute documents necessary to effect the financing.

City officials said the expansion is primarily intended to manage stormwater flows that now overwhelm the plant during heavy rains, allow routine clarifier maintenance without endangering compliance, and reduce the city's long-term maintenance costs. The council thanked staff for the presentation and moved to next agenda items.

The resolution was read into the record as "City of Shepherdsville resolution 202601" and the text in the public record includes the assistance agreement authority and an effective date clause; council discussion and a staff briefing provided the engineering and schedule details summarized above.

Next steps: the mayor and city clerk were authorized to execute the necessary documents to effect the financing; staff will continue project planning and report back to council with implementation details and timelines.