Votes at a glance: Muskegon County Public Works approves vehicle purchase, contracts, PFAS-related work and routine procurement
Summary
At its May 14 meeting the Muskegon County Public Works Board approved a set of purchases, contract amendments and bids — including a pickup truck for landfill fire response, sole-source maintenance rates, pump-station and well rehabilitation contracts, a solicitation for VFDs, and alfalfa sales.
Get email alerts on the Board Votes Roundup topic
No spam. Unsubscribe anytime.
The Muskegon County Public Works Board on May 14 approved multiple procurement and contract items. Key outcomes summarized below were taken from motions presented during the meeting and carried by the board.
- Truck purchase (Item 33): Approved purchase of a 2026 GMC Sierra 3,500 HD 1-ton pickup for $53,197 using the Bridal Cooperative purchasing agreement to transport a 2,000-pound water tank for landfill fire protection. Motion moved by Commissioner Sears, supported by Commissioner Sims. The motion carried; one member (Warren) did not approve.
- Maintenance services amendment (Item 34): Approved a second amendment to the preventative maintenance and equipment repair agreement with McAllister Machinery as a sole-source provider; staff said labor rates will increase (travel labor +2.35%, field repair +7.8%) and a new field-lube labor category was added. Motion carried by voice vote.
- Change order (Item 36): Mentioned change order number 2 with Jackson Murphy Contractors for $1,141,008; board tabled return to this item while proceeding with other items.
- EGLE grant amendment (Item 35): Accepted the 3rd amendment to an Alternative Water Supply Grant (up to $521,400) to support water-main improvements related to the county’s Dalton Township project and potential dam-management responsibilities around Silver Creek Pond. Motion carried.
- Force main engineering (Item 39): Authorized Franin Neuhaus to provide engineering services for up to $443,000 to design relocation of the A-to-C force main; engineering is intended to permit directional-drilling installation below fly-ash contamination. Motion carried.
- Laketon pump station screen (Item 40): Awarded RK Davis Inc. $1,238,000 (RFB20624) to install an automated bar screen with a trash rake to reduce manual cleaning and protect pumps. Motion carried.
- Whitehall purge wells rehabilitation (Item 41): Awarded Jackson Murphy Contractors Inc. $857,086 (RFB20625) to rehabilitate one set of purge wells; staff said EGLE requires continued operation and that PFAS was detected but discharges are within water-quality effluent limits. Motion carried.
- VFD solicitation (Item 42): Authorized solicitation of bids to purchase and install six variable frequency drives (VFDs) for C Station lift pumps; funding partially budgeted and to be supplemented from reserves. Motion carried.
- Alfalfa sales (Item 43): Accepted Riesbold Dairy’s bids for alfalfa at specified fields ($43.20 and $45.60 per ton); staff said the bidder was the sole respondent this year. Motion carried.
Board adjourned after reviewing monthly informational reports; Vice Commissioner Arder thanked the county for the recent free-dump-day program.