Unplanned utility work adds cost to new K'8 school; board told Special Facility funds will cover it

Gadsden County School Board · February 24, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff told the board that overhead utilities at the new K'8 school site must be converted to underground and that conversion was not included in the guaranteed maximum price; Mr. Hudson and Superintendent Elijah Key said the additional cost will be charged to Special Facility funding and staff updated the board on demolition, land clearing and a dedicated Head Start electrical pole.

Mr. Hudson, a district staff member working on facilities, told the board the K'8 school project has encountered overhead utility lines at the King Street/Shanks Middle School site and that "the utility must be converted to underground," work he said was not included in the guaranteed maximum price (GMP).

Board member Stacey S. Hannigon said some members lacked the earlier packet showing approval of the GMP and asked whether the newly identified work had been accounted for. Dr. Sylvia Jackson said the previously approved GMP document may describe categories of potential work in general terms but not a detailed line-by-line allowance. Charlie D. Frost asked whether the work would be added to the GMP or was an as-needed cost; Mr. Hudson said it was the latter.

After questions from the board, Mr. Hudson and Superintendent Elijah Key explained the district would charge the extra cost to Special Facility funding so state accounting would remain balanced. Mr. Hudson also provided progress updates on land clearing and demolition and referenced a new electrical pole placed by the city to provide dedicated service to the Head Start building.

Why this matters: converting overhead utilities to underground can add both schedule complexity and cost to school construction projects. Board members raised packet and transparency concerns about how unforeseen site work is described in GMP materials and asked staff to clarify which items are guaranteed costs versus contingency or change orders.

The board did not vote on any contract changes during the workshop; staff said abatement work is being handled by Southern Earth Sciences under the district's continuing arrangement and that staff will provide further details as procurement and accounting for the work proceed.