County explores historic-preservation grant to shore up courthouse foundation, balconies and windows
Summary
A state grant program that awards up to about $350,000 (50% match required) drew detailed discussion as Daniels County commissioners and an outside grant administrator weighed potential match, project phasing and procurement rules before pursuing an application for 2026–27 funding.
Get email alerts on the Historic Preservation topic
No spam. Unsubscribe anytime.
Daniels County commissioners and their grant consultant discussed pursuing a state historic-preservation grant to address building-envelope work at the county courthouse, including foundation repairs, balcony stabilization and window replacement. Lynette, the county's grant writer from Helena, told the board that applications are due in May 2026, go to the legislature in 2027 and awards are typically announced in June 2027.
Lynette said the program focuses on the building envelope—walls, roofs, doors, facades, windows, foundations and major systems—and requires a 50% local match. She cautioned that costs incurred before the award letter cannot be counted toward the match; in other words, expenditures become eligible only after the grant is formally awarded. The group discussed breaking the work into phases (for example, foundation and balcony work first) and gathering contractor estimates to define a realistic match level.
Commissioners and staff also discussed procurement and bidding thresholds under Montana law. Lynette advised the board to treat the entire grant project as one procurement for bidding purposes—if the total project exceeds the statutory threshold (discussed in the meeting as $80,000), the county must follow Montana solicitation rules rather than treating subcomponents separately.
The board identified next steps: obtain contractor estimates for foundation and balcony work, review the county match capacity, and prepare to start grant application work in March 2026 when final guidelines are expected. Commissioners noted a smaller electrical improvement estimated at roughly $5,000 may be pursued sooner to reduce rental costs for county office space, but Lynette advised staff it likely could not be used as match until an award letter is issued.
Why it matters: A successful award could effectively double locally available dollars for courthouse repairs (for example, a $150,000 local match could leverage roughly $300,000 in total project funds), reducing the county's direct construction burden and preserving an historic building.
What happens next: Staff will gather estimates and prioritize project elements for a grant application. The board asked the grant team to return with cost estimates and a recommended match strategy ahead of a March 2026 application start.