Engineer: Nor‑Bath Trail Phase I to finish this year; extension into borough targeted for 2027, easement work continues on Ciff Cowling Field
Summary
Borough Engineer Ron Madison told council that Phase I of the Nor‑Bath Trail through Keystone Cement should be completed this year and the borough extension targeted for completion by the end of 2027; Madison also reported ongoing survey and easement issues for Ciff Cowling Field involving the Bath Water Authority and the School District.
Get email alerts on the Local Infrastructure topic
No spam. Unsubscribe anytime.
At the May 11 meeting Borough Engineer Ron Madison updated council on the Nor‑Bath Trail and related easement work. Madison said Phase I of the Nor-Bath Trail through the Keystone Cement parcel is expected to finish this year, and the trail extension into the Borough is projected to be completed by the end of 2027. He also reported survey work for Ciff Cowling Field and ongoing easement negotiations involving the Bath Water Authority and the local school district.
Council treated the update as in-progress business; staff will continue survey work and coordinate necessary easement agreements before trail and pavilion work advances. The item remains open and referenced elsewhere in the meeting packet and engineer reports.
Next steps: continued survey work and easement negotiations; schedule and completion dates may depend on inter-agency easement agreements and external approvals.