Summary

Public works staff asked council to authorize contracts to build a one‑mile C‑8 Canal multiuse pathway (FDOT largely funds it) and a separate 1.9‑mile Greenbrier bike‑lane and drainage project that pairs with the village mill‑and‑overlay program.

Public works staff urged the council to authorize two transportation projects that rely heavily on outside grant funding and state agreements.

Project manager (speaker 12) described a one‑mile, 10‑foot multiuse pathway along the C‑8 Canal from Forest Hill Boulevard to Stribling Way. The construction request is $451,000 with $30,000 for construction‑engineering inspection (CEI); FDOT is contributing $355,000 and the village would provide a $95,000 match. Staff said the project must begin by the end of June to meet grant conditions and estimated a 120‑day construction period.

The Greenbrier Boulevard project would add 5‑foot bike lanes each direction along a 1.9‑mile collector road, paired with drainage improvements and targeted roadway raising. Total project cost is $3,677,000 (construction $3,458,000; CEI $219,000) with FDOT funding $2,400,000 and village funding of $1,000,000 (largely from the mill‑and‑overlay program). Staff said plans include preserving existing trees and equestrian bridle trails while narrowing through lanes to 11 feet for traffic calming.

Council members asked who would use the C‑8 pathway and whether it made sense to wait in case roadway widening on Stribling Way would remove space for a future path; staff said the project was prioritized through the MPO and the village must proceed now to secure the grant. Low bidders were disclosed for the C‑8 path and for other projects; staff recommended awarding contracts and executing supplemental FDOT agreements to secure the funding.

Both items were presented as regular consent or action items requiring council authorization to move to construction.