Lake Bluff board authorizes A/C replacement at public works building; waives bids
Summary
Trustees authorized a contract (not to exceed $28,787) with Assurance Heating and Cooling to replace the public works administration building's air-conditioning system and waived competitive bidding after staff found the leak source and cited the federal phase‑down of R410A refrigerant.
Get email alerts on the Facility Maintenance topic
No spam. Unsubscribe anytime.
The Village of Lake Bluff Board of Trustees on May 27 authorized a construction contract with Assurance Heating and Cooling for up to $28,787 to replace the air-conditioning system at the public works administration building and approved a waiver of competitive bidding.
Staff said initial troubleshooting in September 2025 diagnosed a leaking evaporator coil and provided a quote of $11,858 to replace it. Subsequent testing showed the leak originated in the exterior condensate coil, and Assurance revised its quote to $18,473. After comparing quotes, staff recommended replacing the whole system rather than investing in a component-level repair, noting the federal phase‑down of R410A refrigerant and the desirability of installing equipment that uses R454B and has a warranty.
Trustees asked about timing; staff said lead time to obtain the replacement unit is roughly six weeks and that installation is probably mid‑July. Staff also said the system is partially working now and they hope no temporary cooling will be required before installation. The board approved the contract by roll call.