Commissioners approve multiple procurement awards including airport runway rehabilitation conditional on FAA/MAA grants
Summary
The board approved a series of procurement awards and contingent grant‑funded airport projects including a $2.22 million runway rehabilitation bid contingent on FAA/MAA grants, multiple local road and culvert contracts, and several sole‑source maintenance contracts for public safety systems.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
On June 9 the Washington County Board of County Commissioners approved a sequence of contracts and procurement actions covering transportation, airport infrastructure, and several sole‑source maintenance agreements.
Airport projects: Commissioners accepted contingent awards for two time‑sensitive airport projects and authorized staff to submit FAA and Maryland Aviation Administration grant applications. The board conditionally accepted a low bid of $2,220,450 from C. William Hetszer for rehabilitation of runway 2‑20 at Hagerstown Regional Airport and separately approved $92,000 and $2,218,625 contingent awards for the demolition of the old Aircraft Rescue and Firefighting (ARFF) building and airport operations area fence realignment respectively. Staff said FAA/MAA grants commonly cover roughly 95% of eligible costs; the airport enterprise fund would cover the local match if grants are awarded.
Roads and drainage: The board awarded the Sha Walter Road at Pini Avenue intersection improvement contract to Roland & Company for $417,525.50 to install a new signal, auxiliary lane and median—staff cited 10 incidents at the intersection over three years, including three personal injury crashes. The county also approved purchase of a precast concrete box culvert for the Appletown Road project ($114,727.14) and authorized partial property acquisitions and easements for Long Meadow Road and Appletown Road necessary for intersection and culvert improvements.
Sole‑source and software contracts: The board approved multiple sole‑source procurements citing compatibility and long‑standing system use: Keystone Public Safety for CAD interface maintenance ($143,588) for the emergency communications center and ESO Solutions for fire incident reporting maintenance ($109,651.26). The Sheriff's Office received approval for a sole‑source electronic door and intercom upgrade at the detention center ($255,000) from the manufacturer to avoid system downtime.
Other facilities: Commissioners approved the county office building roof repair contract ($292,845) and awarded a $2.8 million contract to renovate the Martin Luther King Jr. Community Center (one commissioner abstained due to a disclosed potential subcontractor conflict). Many awards were approved contingent on available capital funds or grant approvals as noted in staff presentations.
The board instructed staff to proceed with grant submissions for airport items and directed that certain grant documents be executed by authorized board officers once awards are confirmed.