Selectmen revise grant resolution, increase emergency services facility project cost to $12.6 million
Summary
On June 9 the Board voted to revise a previous resolution for an emergency services facility grant: the earlier $10 million figure reflected construction only; after including contingency and the full grant formula the correct project total was stated as $12.6 million and the Board approved updating the resolution.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The Willington Board of Selectmen voted on June 9 to revise a prior resolution tied to an emergency services facility grant application to reflect a corrected project total of $12.6 million.
A presenter explained that the original $10 million figure reflected construction costs only and did not use the full grant formula; when contingency and other line items were added the total rose to $12.6 million. The Board moved to revise the previously approved resolution to state the full project amount for the grant application and approved the change by voice vote. The presenter emphasized this is still an application and no contract award or commitment beyond correcting the resolution was made at the meeting.
The motion to correct the number was approved; the transcript records the motion passing by voice vote but does not record individual roll‑call tallies.