Williston awards $556,000 pump-station procurement for WRRF reuse pipeline

Board of City Commissioners · April 14, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The city accepted Dakota Pump LLC’s low bid of $556,000 for a WRRF reuse pump station, noting a 50–52 week equipment lead time and directing the City Engineer to execute documents to complete the construction contract.

The Board of City Commissioners approved purchase and contract authorization for a reuse pump station at the Williston Water Resource Recovery Facility (WRRF) on April 14, 2026.

City Engineer David Juma reported three bids with Dakota Pump LLC as the low bidder at $556,000 and said lead time is roughly 50–52 weeks, prompting the decision to separate procurement of the pump station from the pipeline work. The council voted to accept the bid and directed the City Engineer to complete necessary contract documents.

The board’s action authorizes staff to move forward with procurement and contract execution; council did not modify the bid award on the floor.