Williston awards $556,000 pump-station procurement for WRRF reuse pipeline
Summary
The city accepted Dakota Pump LLC’s low bid of $556,000 for a WRRF reuse pump station, noting a 50–52 week equipment lead time and directing the City Engineer to execute documents to complete the construction contract.
Get email alerts on the Water Reuse topic
No spam. Unsubscribe anytime.
The Board of City Commissioners approved purchase and contract authorization for a reuse pump station at the Williston Water Resource Recovery Facility (WRRF) on April 14, 2026.
City Engineer David Juma reported three bids with Dakota Pump LLC as the low bidder at $556,000 and said lead time is roughly 50–52 weeks, prompting the decision to separate procurement of the pump station from the pipeline work. The council voted to accept the bid and directed the City Engineer to complete necessary contract documents.
The board’s action authorizes staff to move forward with procurement and contract execution; council did not modify the bid award on the floor.