Redevelopment reviews $256,913 Smith Corp invoice and reports stop-work order after utility strikes

Greendale Redevelopment Commission · April 21, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Commission discussed a $256,913.68 invoice from Smith Corp for a stormwater project; staff said the city issued a stop-work order after several utility strikes and other site problems. Commissioners were told prior agreements designated the board of works to manage project oversight and that some project-management invoices may be the board-of-works' responsibility.

The Redevelopment Commission reviewed claims related to the Smith Corp stormwater project, including a Smith Corp invoice totaling $256,913.68 and questions about which entity should pay project-management invoices.

The commission was told: "just so you're aware, we did issue a stop work order on them yesterday," after several utility hits (sewer main, gas line, fiber), undermined drive apron on Highway 50 and a near-miss with a utility pole feeding a pump. Staff emphasized that while work is stopped, payments for previously completed, invoiced work remain due: "anything past that or previous, you have to pay them for that though."

Why it matters: the city faces a substantial vendor invoice and on-site safety and utility incidents that prompted the stop-work order. Commissioners discussed that the board of works had been expected to manage project supervision and that some Rizzo project-management invoices may not be redevelopment's responsibility.

Next steps: staff said Rizzo and the utility director will verify compliance before allowing the contractor to resume work; commissioners approved the presented claims by voice vote and asked staff to reconcile which invoices redevelopment should carry versus board-of-works responsibilities.