Abutters press for professional restoration at 16 Old Summit; engineer outlines three‑year monitoring plan
Summary
An engineer told the Halifax Conservation Commission he filed a Notice of Intent for 16 Old Summit that will restore pre‑existing contours and include a three‑year monitoring plan; abutters said prior self‑help attempts had worsened the wetlands and asked for qualified contractors and assurances.
Get email alerts on the 16 Old Summit Wetlands topic
No spam. Unsubscribe anytime.
At the June 9 meeting of the Halifax Conservation Commission, engineer Dave Clint said he has filed a Notice of Intent for work at 16 Old Summit Road that seeks to restore contours to their condition three to four years ago and includes a three‑year monitoring plan to ensure vegetation establishes properly.
"I filed a notice of intent ... I have a restoration plan in place with a three‑year monitoring process to make sure everything is done right," Dave Clint said, identifying himself as from Colin Civil Engineering Group. Clint told commissioners that the owner’s earlier cleanup efforts had pushed additional material into the wetlands and that the restoration will remove concrete and misplaced fill and reestablish prior contours.
Abutters Joe and Sam Meline of 10 Old Summit Street told the commission they want the work done by a qualified firm rather than by neighbors attempting to fix the site themselves. "We just want to voice our concerns that the wetlands are restored properly," Joe Meline said. Commissioners acknowledged the concern and said abutters will be asked to sign a letter of consent allowing the hired contractor access to their property for plantings or restoration work.
Staff and the consultant said the Notice of Intent is scheduled to be before the commission at the June 23 meeting. The proposed plan calls for annual checks during a three‑year monitoring period; if planted materials fail, the applicant must replace them until the site is stable. Commissioners emphasized that the town may require an amended order of conditions if the owner seeks to clear additional shoreline vegetation.
Next steps: the NOI is expected at the June 23 meeting; staff will verify the filing and the scope of proposed restoration, and abutters may be asked to provide consent for contractor access.