Lucas County commissioners authorize steps toward comprehensive corrections center renovation
Summary
The Board approved advertising for repairs and solicitations for architecture and construction management services to begin comprehensive renovations at the Lucas County Corrections Center, with commissioners debating renovation vs. new construction and funding challenges.
Get email alerts on the Corrections Renovation topic
No spam. Unsubscribe anytime.
The Board of Lucas County Commissioners on June 2 approved permissions to advertise for repairs and to solicit architecture, engineering and construction management services for comprehensive renovations at the Lucas County Corrections Center.
The move includes: (1) advertising repairs to remediate subsurface moisture intrusion—exterior masonry, concrete and grading and interior concrete and door repairs—and (2) issuing RFQs for professional architecture and engineering services and construction management services tied to a facility condition assessment. Jeff Nowak, presenting for Facilities, said the work follows the department's 2026 capital improvement program and aims to protect the building envelope and life‑safety systems.
The board’s discussion focused on the long history and funding decisions surrounding the county’s jail projects. A commissioner who has participated in the issue for years said, “this is not a new jail. This is rehabilitation of the old jail,” and described earlier efforts to build a new facility, site controversies and limited state funding. The same commissioner estimated that building a new jail would have carried an additional annual cost of about $17,000,000 and argued renovations are the fiscally responsible path for the county.
Another commissioner said the county should continue to pursue state operating budget funding and be “ready to apply” for grants if dollars become available. A separate commissioner emphasized the community will likely bear most costs and urged continuing local lobbying while proceeding with renovations.
The board approved the advertised repairs and the solicitations to identify design and construction management firms. No dollar amounts for the future renovation contract were finalized at the meeting; Nowak noted two separate procurement phases (design services and construction management) will precede any construction contract.
Next steps: the county will issue the advertised repair bid and RFQs; firms responding to the RFQs will be evaluated before returning to the board for contract awards and construction‑phase approvals.