Summary
Beyond the public hearing, commissioners approved a temporary purchasing‑policy exception to repair a recycling truck, awarded a low bid for 52 recycling containers to WasteEquip, and approved multiple roadway and trail contracts (University Park Trail resurfacing, long‑line painting and ditch restoration).
Get email alerts on the Procurement topic
No spam. Unsubscribe anytime.
After adjourning the sanitary‑sewer hearing, county staff presented several routine procurement and contract items. Staff asked the board to bypass the usual purchasing policy to allow immediate repair of a recycling truck by a local vendor that could perform the work without lengthy towing or travel. The chair moved for approval and the clerk called the roll; the transcript records affirmative responses from "Commissioner Cebacki" and "Commissioner Lopez." The transcript does not record a third roll answer in the excerpt.
Staff also recommended awarding a low bid to WasteEquip ("Waste Equipped" in the staff presentation) to purchase 52 recycling containers at the lowest quoted unit price shown in staff materials (~$14.42 per unit). The board then considered and approved additional items presented by county engineering staff, including a professional‑services approval with StreetScan USA to collect pavement condition data, an award of contract to Henry W. Bergman for the University Park Trail resurfacing project at $657,456 (lowest of three bidders), a $252,870 award to Griffin Pavement Striping for the 2026 long‑line painting program, and a $264,240 award to Columbus Landscaping for a two‑stage ditch restoration project (staff said that project is paid for by a U.S. EPA grant). The chair moved for approval of the listed items and the roll calls in the transcript recorded affirmative votes.
The items were presented as routine contract awards and procurement exceptions; staff said they obtained multiple quotes where feasible and described grant funding where applicable. The commission adjourned the meeting and scheduled its next session for June 9 at 11:00 a.m.