Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Transportation topic

No spam. Unsubscribe anytime.

Hayden council weighs temporary traffic signals and up to $48,000 in rental costs during roundabout work

Hayden City Council · June 9, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council discussed temporary portable signals at Hayden & Ramsey and Hayden & Atlas to ease congestion during a three-month roundabout construction window; staff estimated high-end rental costs of $16,000 per month and noted a faster deployment option requiring no right-of-way acquisition.

Hayden City Council members on June 9 reviewed staff recommendations to deploy temporary traffic signals to relieve congestion expected during roundabout construction at Ramsey and Honeysuckle.

Staff explained two tiers of mitigation: short-term portable signal rentals (fixed-time units with potential camera detection) and a longer-term, wood-pole controller installation. The consultant/engineer said fixed-time portable signals would operate better than a four-way stop in peak conditions and could be connected to detection systems if needed.

On timing, staff said the roundabout contractor holds a pre-construction meeting this week and could start as early as Monday, June 15, with the roundabout work lasting roughly three months. A portable-signal rental was estimated at $16,000 per month on the high side; at three months that would total about $48,000. "That estimated cost we got on that would be on the high side would be 16,000 a month," staff said.

Council discussed whether to fund a change order for temporary signals and whether to pursue a more costly wood-pole controller ($100,000 estimate) that would require right-of-way or property cooperation. Staff said temporary units could be deployed in under two weeks once ordered.

Several council members expressed support for approving a future change order to secure temporary signals to reduce summertime congestion and safety risks during construction. No formal budget appropriation or final contract was approved at the meeting; staff will return with a recommended change order or contract terms for council action.