Blue Island outlines water bond spending and long-term needs; residents report water odor
Summary
Councilors discussed the status of $12 million in water bond proceeds, a Burke Engineering estimate of roughly $98 million in long‑term water infrastructure needs, routine water-quality testing that the city said showed no EPA violations, and an isolated report of a 'rotten egg' water odor to be investigated.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
City officials reviewed the status of water‑infrastructure financing and operations during the June 9 meeting.
Administrators said roughly $10–12 million in bond proceeds for water projects are held in a secure account; only limited spending has occurred so far (sewer televising and engineering fees). The administrator said the city needs a completed engineering solution to replace aging tanks without loss of pressure and that the work will likely continue into next year. A staff memo cited a multi‑decade estimate from Burke Engineering that placed long‑term water‑system needs at about $98 million over approximately 20 years.
Officials emphasized that the bond proceeds are to be repaid from the water revenue fund (an abatement), not by a property-tax increase. "Bonding is a dedicated resource to repay these funds," a city official said; in this case water revenue is the dedicated source.
Separately, city staff presented a draft of the annual Consumer Confidence Report for the water system and said recent required testing found no EPA violations. A resident and an alderman reported a transient "rotten egg" odor in the water that the resident suspected was hydrogen sulfide; staff said they would connect the resident to water operators to investigate whether the smell was localized and would review testing results.
Councilors also asked for documentation supporting the $12 million figure and the underlying engineering estimates; staff said the estimate came from earlier engineering presentations and work by Burke Engineering and that additional briefings (including a presentation by engineer Travis Perry) will be scheduled.
What happens next: staff will provide further documentation on the bond proceeds and engineering estimates and will investigate the reported water odor with operators; the council indicated it intends more detailed follow-up briefings on water‑system projects.