Scofield authorizes up to $15,000 to finish Laurel Street; bids to be solicited
Summary
The council authorized up to $15,000 from the B & C Road Fund to complete Laurel Street (Church to Union, 16-foot width), and directed staff to solicit bids. Brad Peacock moved the funding authorization and Kim Erikkila seconded; the motion passed unanimously.
Get email alerts on the Roads topic
No spam. Unsubscribe anytime.
The Scofield Town Council approved a motion on May 11 to spend up to $15,000 to finish Laurel Street from Church Street to Union Street, using road base and additional rotomill sourced from the B & C Road Fund. The council instructed staff to solicit bids for the project and capped the expenditure at $15,000.
Motion and vote: Council member Brad Peacock moved to authorize up to $15,000 and to solicit bids to finish Laurel Street; Council member Kim Erikkila seconded. The motion passed with unanimous assent.
Scope and next steps: The planned work covers a 16-foot-wide roadway and will proceed after the town receives bids. The council scheduled a transfer-of-funds meeting and budget hearings for June 8, 2026 to finalize budget allocations. No contractor was selected at the May 11 meeting.