Boca Raton accepts up to $1 million in state funds for Spanish River Boulevard underpass at El Rio Trail

City of Boca Raton City Council · June 9, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council adopted a resolution to accept a state appropriation of up to $1,000,000 toward a projected $5,000,000 El Rio Trail grade-separation project; staff expects 90% plans soon and a construction start in early 2027.

The City Council voted unanimously to accept up to $1,000,000 in state funds to support the Spanish River Boulevard grade separation at the El Rio Trail project.

Zach Pierre, director of public works and engineering, told the council the funds are provided as a state appropriation (not a grant) and that the city's capital improvement program anticipates the project with an estimated total construction cost of $5,000,000: $1,000,000 in state funds and $4,000,000 in city funds. Pierre said staff expects 90% plans in the next one to two weeks and is targeting a construction start in the first or second quarter of 2027.

Councilmember Drucker emphasized the project's public-safety value, noting prior accidents at the crosswalk and saying the underpass aligns with the city's Vision Zero goals to reduce fatalities.

Council moved, seconded and adopted Resolution 65-2026 by voice vote, recorded as 5-0.

Next steps: Staff will proceed with final design approvals and coordinate construction scheduling and funding as the project advances toward procurement.