Commissioners weigh Scott Park pedestrian upgrades and paving bid awards; engineer recommends mixed-award approach
Summary
Engineers recommended awarding the concrete and pedestrian work for Scott Park and using a change order to the township's 2026 paving contract to finish paving, citing grant funding (about $258,227) and base bids; commissioners agreed to proceed with the HVAC purchase and to rebid the admin roof separately.
Get email alerts on the Park Improvements Paving topic
No spam. Unsubscribe anytime.
Township engineering staff presented detailed plans for Scott Park pedestrian improvements on June 9, including new crosswalks, sidewalks, a road diet to narrow a driveway and three speed tables. The project drawings included solar-activated crosswalk signs and new striping intended to improve pedestrian safety in the park.
The engineer said the base bid for the pedestrian and concrete work was $392,675 and that the township had a related grant award of $258,227 toward the project. Two ad alternates for additional paving were priced at approximately $65,038 but were reduced to an estimated $58,000 after cross-checking unit prices with the township's paving contractor. The engineer recommended awarding the base pedestrian/concrete work to Independent Enterprises and using a change order to Youngbloods' 2026 paving contract (estimated $77,904) to complete the related paving economically.
Commissioners discussed sequencing: they agreed to proceed with replacing two HVAC units (quoted together at $30,980) to avoid having to re-roof patched areas later. The engineer also recommended rejecting the admin roof bid and rebidding it in early winter when more competitive pricing is likely.
No final contract award was recorded in the public discussion on June 9; staff said they would return a formal award recommendation and contract documents at a future voting meeting. The engineer described available budget capacity (approximately $2.95 million awarded to date with contingency) and said roughly $150,000 would remain in contingency after recommended awards.
The next steps enumerated by staff were to (1) finalize bid tabulation and references, (2) prepare award resolutions for an upcoming voting meeting, (3) execute HVAC procurement to align with roofing schedule and (4) proceed with grant application deliverables and reporting tied to the Scott Park project.