Lynn Haven commissioners direct staff to draft one-year moratorium on AI data centers

Lynn Haven City Commission · June 9, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The city directed staff to draft a one-year moratorium on AI/data-center relocations while officials update land-use rules and study environmental and utility impacts. Commissioners said the pause would create time for the Unified Land Development Code review; staff noted limited suitable sites.

The Lynn Haven City Commission voted to direct staff to draft a one-year moratorium on artificial intelligence data-center relocations to the city, saying the pause will give planners time to update land-use regulations and study potential impacts on water, power and other infrastructure.

Commissioner Sam Warick, who introduced the proposal, said the moratorium would run while the city’s Unified Land Development Code is revised. “A one-year moratorum would give us the opportunity to get our ULDC up to snuff and up to par,” Warick said, adding that the pause is intended to preserve officials’ ability to evaluate applications with up-to-date rules.

City attorney Mr. Jackson told the commission that a short moratorium is a customary legal approach to give the city time to assemble evidence and findings before adopting permanent restrictions. “The purpose of a moratorum is to put potential applicants on notice,” Jackson said, “study the issue and then come back with the results.”

City staff told commissioners they currently see limited parcels inside Lynn Haven suitable for large data centers and that utility-capacity analysis would be required for any development order; if the city cannot demonstrate adequate water or sewer capacity, staff said a development proposal could be denied through the normal process.

Several commissioners urged coordination with Bay County, which has considered similar measures. Staff recommended waiting to see county actions but expressed no legal objection to proceeding at the city level. After discussion the commission approved the directive to draft moratorium language and to have staff report back with findings and recommended ordinance language.

The commission did not adopt a permanent ban; rather it directed staff to prepare the moratorium text and supporting study for future consideration.

Next steps: staff will draft moratorium language, analyze likely impacts on utilities and the environment, and return with findings and a proposed ordinance for the commission to consider.