Callaway approves impact-fee purchase to upgrade failing South Gay water loop and add hydrants

City of Callaway Board of Commissioners · June 9, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Commission approved using water impact fees to replace a failing 2-inch galvanized loop with a 6-inch main, complete the loop and add two fire hydrants; staff said three quotes were received and work will be done in-house with materials purchased from Empire Pipe (lowest quoted amount ~ $17,427).

City staff told the commission they identified about a 1,000-foot run of 2-inch galvanized looping pipe on South Gay Avenue that is failing and not performing as intended when connected to larger mains. Staff recommended upgrading the segment to a 6-inch main, installing two additional fire hydrants, and funding the materials from water impact fees while performing labor in-house.

“We've been replacing service lines and adding chase pipes under there. Our goal is to once we pave this road, we won't be doing any road cuts in the future. . . we would like to go ahead and use water impact fees, upgrade that line to a 6 in. . . and we'll also be able to add two fire hydrants to that area,” the city manager said.

Staff said the upgrade is below the city's $25,000 threshold for formal procurement and that they received three quotes; the lowest quote, cited by staff, came from Empire Pipe at about $17,427 (materials only). Commissioners asked whether shipping was included in the quote; staff said the quote showed no freight line and they had included a not-to-exceed instruction to prevent cost overruns.

The commission approved the use of impact fees and the materials purchase by voice vote.

Why it matters: Upgrading to a larger-diameter main should improve pressure and service reliability in the area, and adding hydrants is intended to improve fire protection coverage. Staff said doing labor in-house will reduce overall cost compared with a contractor-led installation.

Next steps: Staff will order materials, perform the installation in-house and coordinate final paving with the scheduled South Gay Avenue repaving project.