Marion County approves $10,114.25 change order for Junction 92 engineer office; contract rises to $592,442.20
Summary
On May 26 the Marion County Board approved Resolution 2026-69 to accept Change Order No. 2 from RG Construction, LLC, increasing the Junction 92 engineer office contract by $10,114.25 to a total of $592,442.20.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The Marion County Board of Supervisors approved Change Order No. 2 for the Marion County Engineer's office building at the Junction 92 facility on May 26, 2026, increasing the contract sum by $10,114.25.
Resolution 2026-69 authorizes the county to accept the change order from RG Construction, LLC. The change brings the contract total from $582,327.95 to $592,442.20. The board voted to approve the resolution on a motion moved by Supervisor Steve McCombs and seconded by Supervisor Jim Mueller; roll call recorded Ayes: McCombs, Jahner, Mueller.
According to the minutes, the change order reflected two change requests initiated by the Marion County Engineer and accepted by the county; the minutes do not list the specific work items included in the change requests. The board’s action instructs county staff to proceed with the adjusted contract amount; no additional funding source or contingency was stated in the meeting minutes.