Paragonah tabled lead-service-line replacement; pre-bid work continues on water improvements
Summary
The board declined to move forward immediately with a full lead/copper line replacement after testing suggested Paragonah lacks those service lines, and set a June 16 pre-bid meeting for the broader water improvement project with bids expected in July.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
The Paragonah Town Board on June 10 decided not to proceed at this time with a mass lead/copper service-line replacement project after staff said sampling indicates the town likely does not have lead service lines. The board instead advanced work on a separate water improvement project and scheduled a pre-bid meeting.
Staff reported the town completed PFAS testing and submitted required reports; the consumer confidence report also was filed and posted online. The lead/copper replacement option discussed during a video conference with the state water board would have been expensive, and members said they preferred to wait unless testing or evidence showed a local need.
The town set a pre-bid meeting for June 16 with engineers and contractors, and anticipated closing bids around July 1 with public opening soon after. Officials said contractors could expect late‑July or August starts depending on lead times. Contract durations discussed included 210 days for substantial completion and 240 days for final completion, subject to weather and supply availability. The board also covered technical details such as well-site markings, tank material tradeoffs (steel vs. concrete) and the need to verify survey stakes where ribbons and wooden stakes were reported missing.
No formal procurement award occurred at the meeting; the board directed staff to verify survey marks and continue with the bidding timeline. PFAS and consumer‑confidence submissions were reported as complete.