Craig council approves emergency valve change and awards north clarifier rehabilitation contract
Summary
Council approved a $27,500 change order to install an interim butterfly valve for a raw water control project to avoid supply risk while a long‑lead plug valve is ordered, and awarded the North Clarifier rehabilitation bid for $162,427 to the low bidder after engineering review.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
City staff told council on March 25 that an urgent operational gap in raw water control required a short‑term equipment substitution. Water/Wastewater Director Carl Ray said the plug valve specified in the original design carries a roughly 30‑week lead time, which could leave the water treatment system vulnerable if spring runoff arrives early or with high flows.
"The plug valve has a 30‑week lead time," Carl Ray said. "A butterfly valve can be delivered in seven days and allow us to operate the vault now; it can later be used as an isolation valve while we drop in the plug valve when it arrives." The council approved a $27,500 change order to purchase and install the butterfly valve as an interim measure; staff said the plug valve will still be ordered and installed when available.
Separately, staff presented results of a competitive procurement to rehabilitate the wastewater plant’s north clarifier. Two bids were received; engineers reviewed schedules and references and recommended the lower bid (base + alternate) at $162,427. Council approved awarding the contract to the recommended bidder and directed staff to proceed with scheduling.
Funding notes: staff said a $50,000 DOA grant will contribute to the raw water control project; the change order and contract awards were presented as necessary to maintain system reliability and meet project timelines.
Why it matters: The interim valve and clarifier repairs are intended to protect drinking‑water production and wastewater treatment operations, reducing the risk of service interruptions during high runoff and sustaining long‑term treatment infrastructure.