Rico trustees press Atlantic Richfield over road contamination, delay RFP pending clearer remediation plan

Town of Rico Board of Trustees · April 16, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Trustees and residents pressed Atlantic Richfield and staff over sampling methods and a mapped remediation plan under the voluntary cleanup agreement; staff recommended delaying an RFP and asked AR to provide clearer sampling, operations/maintenance and funding commitments before construction.

The largest portion of Ricothe April 15 meeting centered on the town's voluntary cleanup program with Atlantic Richfield (AR) and how to handle discolored road segments and stormwater controls.

Staff presented AR's April correspondence and said consultants sampled multiple sites and proposed near-term best-management practices and contractor work; AR planned to deliver a more detailed plan by the end of April. Trustees and at least one public commenter disputed the adequacy of AR's sampling protocol and depth, citing historic deeper samples and arguing that surface-only screening might understate buried contamination.

"To say the bioavailability is not a concern on our streets is not accurate given the way of life of everybody in this town," one trustee said during a sustained exchange in which board members urged firm, time-bound commitments. Trustees noted children, pets and pedestrians use unpaved town streets and asked AR to expand sampling and to fund remediation that prevents repeated excavation and rework.

Staff described the remediation map AR provided: green sections represent core stormwater controls AR will fund and construct, darker-blue sections are next-priority connections AR would build if grant funding is available, and teal areas are lower priorities. Trustees urged AR to reconsider adding certain blue segments (notably Silver and Soda Streets) to avoid channelized flows that could concentrate contaminated material during storm events.

Trustees and staff discussed funding mechanics. Staff estimated the overall stormwater-plus-road remediation program at roughly $4 million; AR has committed roughly $2' million to portions of the work, leaving grant or town match funding gaps and questions about timing. Staff said some incremental-cost reimbursements to the town are included in the current agreement but pressed AR for clarity about on-site testing and replacement of contaminated soils exposed during construction.

Given the uncertainties, staff recommended and trustees agreed to delay releasing the RFP for road construction until AR supplies updated sampling results and a plan that addresses potholing verification, deeper 0—2 inch-zone testing and a clear schedule. The board asked staff to request AR's promised materials in time for the May packet; trustees said a timely, specific response is essential to avoid repetitive negotiations during construction.

Public commenters urged deeper testing in channels that will be excavated for stormwater and called for assurances that contaminated material would not be discharged to state waters. One resident asked how soils excavated under local sidewalk/curb improvements had been handled in prior projects and whether material had been placed outside repositories.

Town staff and legal counsel said many excavation-related incremental costs and trucking to repositories are contemplated in the agreement; trustees said they want explicit written commitments so the town will not be left covering large remediation bills if further contamination appears during construction.

Staff will follow up with AR, request the promised April materials and return a status update and any revised design or RFP language to the board at the May meeting.