Board approves cafeteria flooring change and $29,670 dryer and ventilation project
Summary
Board members approved a $19,132 change order to switch cafeteria flooring to a long-term material and authorized a $29,670 contract for two dryers and an industrial ventilation/lint-control system after hearing project updates that classroom renovations remain on schedule.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
Facilities staff told the board that classroom renovations across the high school's eastern section are progressing on schedule with Menders Construction. The board approved multiple facilities actions, including a flooring change order and a laundry ventilation and dryer replacement project.
For parts of the cafeteria renovation staff recommended replacing the originally specified epoxy flooring with an alternative (LVT-type) surface. The board approved the change order at a cost of $19,132 for tiled areas.
Separately, the board reviewed two vendor quotes for replacing a dryer that was rendered unusable after a ventilation-related fire and for installing an industrial fan and clean-out to control lint and reduce fire risk. Staff recommended the lower-priced bid that meets the district's needs; the total project cost was announced as $29,670 and approved by the board.
Board members discussed scope and installation logistics during the presentation. Both motions were approved by voice vote.