Housing board approves small change orders and grants National Grid easement to widen sidewalk near Fonseca School
Summary
The board approved a $4,375 increase for tree removal and ADA work at Elmer and Corbett streets and a $90,351.11 increase for building and site upgrades at Maple Gardens; the board also ratified an easement allowing National Grid to relocate a pole to permit sidewalk widening for Fonseca School (one abstention).
Get email alerts on the Construction Change Orders topic
No spam. Unsubscribe anytime.
The Fall River Housing Authority board approved two change orders and ratified an easement for a utility relocation affecting Oak Village and the Fonseca School sidewalk.
Change Order No. 1 for site improvements and tree removal at Elmer and Corbett streets (EOHLC number 09-5205) increased the contractor’s price by $4,375 to create more consistent flat parking surfaces and to meet ADA requirements, and extended the contract time by 30 days. The board voted to approve the change order.
The board also approved Change Order No. 1 for comprehensive building and site upgrades at Maple Gardens (EOHLC number 095177), increasing the contract by $90,351.11 to cover: replacing water shutoff valves; relocating electrical panels in buildings 15–17; extending electrical secondaries at building 17; exploratory abatement work at building 18; and abatement pipe insulation. A staff member (Theo) told the board the original contract amount was "just under 9 million." No contract time increase was recorded for this change order.
Under miscellaneous business, the board ratified an easement for National Grid at Oak Village to relocate one telephone pole and a pole anchor onto Oak Village property, moving the anchored pole approximately 6 feet from its original location to allow the city and school department to widen the sidewalk down to Fonseca School. The easement was recommended by staff and approved; one member (David) abstained, citing a connection to Oak Village.
The transcript records motions, seconds and voice votes approving these items; the meeting did not produce a roll-call vote tally for these approvals. The actions appear in the meeting transcript at SEG 284–SEG 341 (change orders) and SEG 344–SEG 390 (easement).