Commissioners approve Dalton‑Whitfield landfill expansion after plan review
Summary
The Whitfield County Board of Commissioners voted 3–0 to find the proposed Dalton‑Whitfield Solid Waste Authority Phase 6 landfill expansion consistent with the county solid-waste plan and zoning, a required step before the authority seeks a permit from state regulators.
Get email alerts on the Solid Waste topic
No spam. Unsubscribe anytime.
The Whitfield County Board of Commissioners on a 3–0 vote approved a formal determination that the proposed horizontal and vertical expansion (Phase 6 MSW) of the Dalton‑Whitfield Solid Waste Management Authority landfill is consistent with the county's solid‑waste management plan and local zoning.
The vice chairman read a letter into the record stating the expansion—identified by permit number 155‑047DSL and located at 4189 Old Dixie Highway, Dalton—complies with the county-adopted plan (September 2018) and local zoning, and that the county zoning administrator concurs. Commissioner Jones moved the finding, Commissioner Thomas seconded, and the motion passed unanimously.
The letter included parcel identifiers for the affected property and adjacent parcels and will be sent to the solid‑waste authority and state regulators. A county representative noted this step is a formality required after state law changes that altered review timing and described the action as the third public meeting on the project since 2024.
There was no recorded public opposition during the item and no amendment to the proposal. The decision recorded by the board is procedural—confirming plan and zoning consistency—and does not itself issue or deny any state permit. Interested residents and agencies will continue to use the standard state public‑notice and permitting processes for any air, groundwater or landfill‑permit approvals.
What happens next: the authority may proceed with the state permitting steps; county staff will forward the county's consistency letter to the authority and state regulators.