Council approves Bransum Paving task order for FY27 resurfacing and parking-lot repairs

Manassas Park City Council · June 2, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved a task order with Bransum Paving Company to resurface 11 roadway segments (quote $657,139 plus a 10% contingency not-to-exceed $722,714.40) and authorized resurfacing of two community-center parking lots (quote $163,149.50; with 10% contingency $179,464.50).

The Manassas Park City Council on June 2 authorized the city manager to sign task orders with Bransum Paving Company for FY27 pavement work and parking-lot resurfacing.

Calvin Odell, director of community development, said staff requested quotes for 11 roadway segments that scored between 16 and 26 on the pavement-condition index; the vendor quote for the 11 segments was $657,139. Odell recommended adding a 10% contingency to cover potential base repairs, bringing the not-to-exceed figure to $722,714.40. The listed roadway segments included Digital Drive; Baker Street (Sheldon to city limit); Shannon Street and Jenna Court; Williams Street; Kirby Street (Pulk to Cabel); Matthew Drive (Southwit to Kevin Court); Spruce Street (Adams to Old Centerville Road); Denver Drive; Hardy's Drive and Hedgeford Street (the previously unpaved section), among others.

Separately, staff presented a quote from Bransum to resurface the main and staff parking lots at the community center for $163,149.50; with a 10% contingency the not-to-exceed amount is $179,464.50. Staff said the parking-lot work fits within the originally intended FY26/27 budget lines for public parking repairs.

During discussion council members asked about sequencing—particularly delaying paving on Manassas Drive while adjacent theater construction is ongoing—and staff said they can defer high‑risk segments until construction traffic subsides. Odell said carrying the FY26 remainder forward and using the additional-streets capital line would leave roughly $190,000 available after these projects, depending on final invoicing and contingency use.

Motions: Council moved, seconded and approved staff recommendations to authorize the city manager to execute a task order with Bransum Paving Company for the 11 resurfacing segments (not to exceed $722,714.40) and to execute a task order for the community-center parking-lot resurfacing (not to exceed $179,464.50). The transcript records the motions as carried by voice vote; the meeting record does not include an itemized named roll-call tally.