Commission approves $157,550 change order to lower HVAC rooftop units at the law enforcement center

Cole County Commission · May 19, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

After contractor and staff explained safety and roof-damage concerns with originally specified curb adapters, the commission approved change order No. 1 to replace rooftop curb adapters at the law enforcement center at an added cost of $157,550.

County staff and representatives from United Mechanical Services explained that the originally specified rooftop curb adapters for the law enforcement center would leave HVAC units 8–12 feet off the roof, creating safety and serviceability risks and increasing the likelihood of roof damage. United Mechanical's representative George Clapper was present for the discussion.

Staff recommended changing to a different curb adapter design that would place the units lower on the roof and reduce the need for ladder work, lowering safety risk and cutting long-term roofing repairs. Commissioners were told the alternative adapters add $157,550 to the project price; staff said the overall project remains under the original budgeted amount.

Commissioners discussed whether to approve the change order immediately or add it into a final combined change order. A motion to approve change order No. 1 for the law enforcement center rooftop curb adapters carried by voice vote.

The commission did not specify finance coding in the meeting discussion; staff noted funding remains available within the project budget and that temporary cooling strategies will be used to keep jail pods operating during work.