Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Contract Performance topic

No spam. Unsubscribe anytime.

Residents press council over unfinished Heritage Landing erosion project; county cites liquidated damages

St. Charles County Council · June 8, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Neighbors reported an unfinished erosion remediation project in Heritage Landing, asked the council to use the contractor’s performance bond or seek reimbursement; the county executive said the contractor is $140,000 in liquidated damages and staff will press the contractor daily while weighing bond options to avoid losing ARPA funds.

Several residents told the council the erosion‑remediation job at Heritage Landing (Nachez) remains unfinished and creates safety and property‑value concerns. Speakers said the contractor has been absent for long stretches and described exposed slopes and damaged yards.

Resident Thomas said his repeated contacts with the contractor produced promises that were not kept. “They showed up one Friday and worked eight hours... We haven’t seen them since,” he told the council, and requested a stronger county response. Another resident, Clifford Morris, said temporary easements were signed and work promised for the prior October had still not been properly completed.

County officials said the contractor has accrued approximately $140,000 in liquidated damages and that payments have been withheld. The county executive said staff threatened to revoke the performance bond to spur work but is cautious because pulling the bond can delay completion further and jeopardize ARPA reimbursement for the project.

Officials committed to daily follow‑up and said if the contractor does not resume work promptly, the county will engage the bonding company to bring in another contractor. Council members expressed frustration at the delay and urged the executive to use available remedies while protecting grant funds.

Residents asked the council to seek a more immediate remedy, including using withheld payments to hire another contractor or pressing the bonding company to act. County staff said they will continue to press the contractor and evaluate bond action if the company does not return to the site.