Council extends Main Street beautification project deadline to December
Summary
Council approved an amendment to extend the Lamar Main Street beautification contract for Royalty Construction LLC to December 31, 2024; contractor has completed benches and trash cans and is finishing decorative pole painting.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
Council approved an amendment extending the completion deadline for the Lamar Main Street beautification project to December 31, 2024.
Martha B. Alvarez told council the contractor (Royalty Construction LLC) is about halfway through painting decorative poles, has finished wooden trash receptacles and benches, and asked for a short extension to ensure the work is completed. Council reviewed the amendment language and confirmed it covered the decorative poles within the Main Street District and that other terms of the original contract remain in effect.
A motion to approve the contract amendment to extend the deadline to December 31, 2024 passed unanimously.