North Berwick OKs $376,207 design contract with Port City for new fire and rescue station

North Berwick Select Board · May 19, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Select Board authorized a $376,207 contract with Port City Architecture for programming, design, engineering and construction administration of a new phased fire/rescue facility, approving a project estimated at roughly $4.7 million in hard and soft costs and targeting a spring 2027 construction start.

The North Berwick Select Board voted May 19 to award Port City Architecture a $376,207 contract to design and administer a new fire and rescue station, part of a project with total estimated construction hard costs near $4.346 million and overall construction and architectural costs of about $4.72 million.

Dwayne Morin presented a line-item estimate showing permitting, survey and geotechnical work, construction of an 11,000-square-foot metal building, and renovation of the existing 2,529-square-foot facility. Morin said the project is phased so rescue operations can continue in the current building while work proceeds on a new rear building.

The contract amount approved covers programming, design, engineering and construction administration; reimbursable expenses and a modest contingency were included in the town’s packet. Selectperson Jonathan Hall moved to enter the contract and Selectperson Wendy Cowan seconded; the board approved the motion 5-0.

Morin said the current schedule envisions permitting by the architect in November 2026, bidding and a guaranteed maximum price in winter 2027, and a construction start in spring 2027 with an estimated 18-month build that could complete in late winter or early spring 2029.

Board members discussed options to reduce costs, including performing landscaping in-house after construction, and noted the town is waiting on grant paperwork from Sen. Collins’ office that could offset portions of the project. Morin said he left contingency and soft-cost balances to cover unexpected items.

The board also authorized staff to issue a Request for Qualifications for construction managers to local firms and set a tentative schedule for questions, submittals, interviews and selection.

The contract approval is a formal authorization to proceed with Port City as the architect of record; subsequent construction-manager selection and the GMP must still be finalized before work begins.