District details $466 million 'Safer, Stronger 204' plan and major renovation for Hill Middle School
Summary
Indian Prairie CUSD 204 staff and consultants presented an update to the board on the $466 million Safer, Stronger 204 capital program, including accelerated financing, $125 million of summer work, a reallocation of about $6 million to expand Hill Middle School's scope and a proposed ~16,000 sq ft addition to correct circulation, expand science labs, and add a secure vestibule.
Get email alerts on the School Facilities topic
No spam. Unsubscribe anytime.
Indian Prairie School District 204 staff and outside consultants on Monday laid out a multi‑year schedule for the district's $466 million Safer, Stronger 204 capital program and unveiled a proposed redesign and addition for Hill Middle School.
The district said the program is funded primarily by a $420 million bond referendum, with about $46 million from other sources including investment earnings and grants. "We are in a position to accelerate some of our financing plans to to potentially coordinate that accelerated timeline as well," the lead presenter said, describing a plan to move Gregory Middle School construction two years earlier and save roughly $6 million that can be reallocated to Hill and other projects.
Why it matters: the board characterized the work as both safety upgrades and equity repairs. Presenters emphasized that secure vestibules, door and access‑control upgrades and a districtwide phased program will be completed over several summers; the work beginning this summer is the mid‑phase of that three‑year rollout.
What was proposed for Hill Middle School: the design presented includes a single‑story main entrance and a two‑story academic addition totaling just under 16,000 square feet, releveling the cafeteria and library to improve circulation, enlarging science labs (bringing them closer to the district average), adding flexible small‑group and collaboration spaces, and building a secure vestibule so visitors must enter through the main office. "Out of your seven middle schools, Hill Middle School was your first middle school built in 1980," the Hill principal said, adding that the building has remained largely unchanged since a single 1992 addition.
Interior changes shown in renderings would add about 46 teaching stations, increase science lab area roughly to district norms (from about 25 sq ft per student to a larger standard), expand the student commons/cafeteria with new skylights and flexible seating, and convert cramped staff and library spaces into openly connected collaborative areas. The presenters said science labs will be physically relocated nearer the front of the building and that the plan creates small pull‑out rooms for testing and one‑on‑one instruction.
Phasing and timeline: the team presented a phased schedule that uses winter and spring breaks for ‘‘enabling’’ work, substantial summer work when students are out of buildings, and temporary mobile classrooms on site while the addition and library are completed. The plan expects the addition and library to be online by January following the main construction season, with final renovation work completed in summer 2028 so the building is fully occupied for the 2028–29 school year.
Budget and program context: the presentation described about $125 million of projects actively underway this summer across nearly every district school and the creation of a $2 million category for "modernizing learning environments" (small refreshes across all 34 schools). The presenters said accelerating select projects can reduce escalation costs and reallocate savings to expand the Hill scope.
Board reaction and clarifications: trustees asked about stair widths, number and distribution of science labs, parent access to the secure vestibule, and furniture durability. The team clarified that the plan provides two science rooms on the first level and three on the second and that parents will only reach student spaces by being buzzed through the office.
Next steps: the district said it will post a semiannual report and capital‑program updates online and continue design development with community outreach and construction phasing. The board will receive further updates as the Hill plan proceeds to final design and contract phases.