Board approves $25,000 CNR request for Macau Circle pipe cleanout after 2024 storm damage

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Board of Finance approved $25,000 from CNR to fund an exploratory mechanical cleanout of a large drainage pipe on Macau Circle that was clogged after the August 18, 2024 storm; FEMA previously provided $46,000 for related debris removal and the town said the low-impact option could avoid a $300,000'$350,000 excavation.

The Board of Finance on June 9 approved $25,000 from the town's CNR account to pay for an exploratory mechanical cleanout of a clogged drain pipe on Macau Circle, a project officials said could avert a much larger excavation.

Public Works Director Eric Schwzman told the board the pipe was severely obstructed after the Aug. 18, 2024 storm and that camera inspections showed a short but badly clogged segment. He said the town found a contractor willing to attempt a limited, less-invasive removal using small equipment rather than full trenching and excavation.

"We're not 100% guaranteed, but pretty sure this is going to work," Schwzman said, adding that the project starts with an exploratory day. The contractor quoted roughly $5,800 per day for on-site work; town staff said a worst-case scenario of 10 days would push total costs higher, and that contingency and reimbursement calculations explain the $25,000 request.

Town staff explained the math to the board: FEMA previously provided a $46,000 debris-removal grant for related storm work, and the CNR request is intended to cover the local share of the remaining expense. Officials said CNR-eligible costs are expected to be reimbursed at about 75% under the applicable program.

Board members questioned where the pipe discharges and about long-term mitigation. Schwzman said the pipe outlets to a nearby creek and that any mitigation or grading to reduce future rock buildup would be a separate project. He warned that if the mechanical approach fails, a full excavation could cost roughly $300,000'$350,000 and would be far more disruptive to yards, driveways and utilities.

The board voted to approve the $25,000 CNR request. Next steps include the exploratory work and a status report if the contractor determines the mechanical approach will not succeed.