Coopertown renovation near completion; contingency remains as work shifts into summer

Haverford Township SD Board of School Directors · June 12, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Officials reported Coopertown Elementary is roughly 80—85% complete: kindergarten wing painting and flooring, main entrance and gym progress, kitchen demolition, and solar arrays scheduled; remaining work centers on flooring and site items with about $600,000 in combined contingency/allowances.

District construction managers briefed the Haverford board on the Coopertown school renovation, saying work is largely on track but finish-line tasks and the gym floor will dictate an exact reopening date.

Ken and Randon updated the board on June 11: the kindergarten wing is painted and flooring begins next week; the main entrance and mechanical work are underway; two rear additions are finished; and the kitchen demo is complete. "We're in the home stretch," one project manager said, estimating the total project roughly 80—85% complete.

Budget and schedule: Staff reported about $420,000 in contingency and roughly $180,000 in allowances remain. "That leaves about $600,000 total of contingency and allowances," the manager said. They noted the gym floor remains the schedule-critical path item and could push some completion work into late summer or early September, though teams are aiming to finish earlier.

Solar and next steps: Solar-panel installation on Coopertown is due to begin over the summer as part of the electrical contract; Chattam Park solar work is also planned for mid-July with a multiweek installation window. Staff committed to sending weekly progress updates to families as the district approaches the opening of the next school year.

What's next: Construction teams will continue summer installations and provide visual progress updates for the board and families; administrators plan regular communications so families know timing and contingency.