Hall County hears update on next‑gen radio system as rural fire departments flag costs
Summary
County radio lead reported 98.5% handheld coverage test results and a spring cutover timeline; volunteer fire officials raised concerns about interoperability and $8,000 handheld costs that exceed small departments' budgets, and commissioners urged grant searches and coordination.
Get email alerts on the Radio System topic
No spam. Unsubscribe anytime.
Hall County officials received a progress report on the county's next‑generation radio system and discussed the financial and interoperability challenges facing volunteer fire departments as they transition to new radios.
John Roseland, the county's radio project lead, told the board that Motorola coverage testing showed roughly a 98.5% handheld pass rate across the county after driving every square mile with a test device. "Sitting at about 98% passing rate," Roseland said, adding that the test simulates handheld radios on the hip, the most demanding use case.
Roseland said two of four contracted payments to Motorola have been made and described a cutover timeline: dispatcher training delayed into mid‑March, cutover likely in late March or early April, and final acceptance around mid‑April. He also noted the first year of maintenance is included in the contract and annual maintenance charges begin after final acceptance.
During public comment, Wood River volunteer firefighter Todd King Woodruff (who identified himself to the board) said interoperability with neighboring Buffalo County remains a problem and that handheld units cost about $8,000 each, far above older radios. "Funding is becoming a problem when we're capped at 1 and a half percent on our rural fire budgets," Woodruff said, explaining many small departments will need to bond or seek grants to purchase equipment.
Commissioners acknowledged the funding gap and encouraged departments to seek grants; one commissioner suggested county staff continue to identify grant opportunities and other funding pathways. Roseland also described a state‑provided 800 MHz tower site (Carroll/Caro Tower) the county will use without paying construction costs for the tower equipment, although the county will need to purchase a building at the site to house the gear.
What to watch: the county plans cutover this spring and final acceptance mid‑April, at which point maintenance contracts will begin and some departments will need to decide how to fund new handsets. The board discussed coordinating updates and potentially scheduling quarterly emergency‑management check‑ins with city and county stakeholders.