Commissioners approved support signatures for three zero‑match road or bridge grants totaling roughly $14.97 million in project estimates and awarded a $662,250 contract to crush aggregate for county road maintenance, authorized for signing outside the meeting to expedite work.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
Commissioners on June 10 approved support signatures for three county grant applications to fund road and bridge work and awarded a separate contract to supply crushed aggregate for road maintenance.
Brad (no title listed in the packet) asked the board to sign three zero‑match grant applications due June 12: Mil Creek paving (listed at about $5.289 million), a Pewitt Bridge replacement project estimated at $4.38 million, and a BLM‑supported project to improve Willard Road to Highway 27 (listed at about $5.3 million). Brad said the higher cost estimates reflect federal delivery requirements via the Oregon Department of Transportation and encouraged prompt signatures; Commissioner Susie confirmed she had reviewed and approved the grants for signature.
The board moved, seconded and recorded a vote in favor of approving signature support for the three grant applications.
Separately, staff reported the county received four bids to crush material in a leased pit to supply road material for district one and district two. The lowest responsible bidder was listed as Forment LLC at $662,250 to crush about 75,000 tons of material. Commissioners moved, seconded and approved awarding the contract and authorized executing the contract outside a formal board meeting so the contractor could finalize bonds and signatures.
County staff said securing the pit and crushed material supply is important given rising prices and the need for aggregate in the upper country districts; the contract will cover material for both Bear Creek and Paulina areas. No further action was requested at the work session beyond authorizing signatures and contract execution.