Engineers report apron, pavement and water-well work at Ennis Big Sky and Ruby Valley Field

Madison County Airport Board · January 12, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Robert Peccia & Associates reported progress on Ennis Big Sky apron expansion and AIP projects; airport staff reported AWOS transformer and runway-light repairs, and QA/QC documentation for public water supply wells was submitted to DEQ with approval expected next week.

At the Jan. 12 meeting, Lance Bowser of Robert Peccia & Associates briefed the Madison County Airport Board on capital-project progress at Ennis Big Sky and Ruby Valley Field airports.

Bowser said preliminary engineering and 25% design work for the Ennis Big Sky north apron expansion is complete and topographic surveying has been finished; the team will schedule further meetings after the 2025 design push. He reported AIP-029-2025 pavement maintenance is complete and the grant is closed. For AIP-027-2023, the Ennis snowplow is complete apart from minor items such as decals and radio installation; a confirmed delivery date is expected before the next board meeting.

Troy Hunter gave an operations update for Ennis Big Sky Airport, reporting that a transformer was replaced to prevent the AWOS from tripping circuit breakers and that a runway-light board had been bypassed while a replacement board was ordered. He noted limited snow removal this winter (about six days) and that staff were working on marketing, updating hangar-owner contact information and securing a company-wide rental-car contract.

For Ruby Valley Field, Bowser said the as-built survey of the airport GIS instrument approach was finalized in December and submitted to the Federal Aviation Administration for chart corrections; additional data collection in leaf-on conditions is planned next spring to support instrument-approach amendments. The board also heard that QA/QC procedures for public water supply wells at both airports are complete and documentation was submitted to the Department of Environmental Quality for review; approval was anticipated the following week.