Groton's RTM unanimously approved a $500,000 appropriation for design and bidding work for phase one of Fish High School stadium renovations; members discussed sequencing of engineering, bidding and bond issuance.
Get email alerts on the Athletics topic
No spam. Unsubscribe anytime.
The Representative Town Meeting approved a $500,000 appropriation for the first phase of Fish High School athletic field renovations to fund design and bidding services.
Chair Watson explained the appropriation is to cover engineering and bid-phase costs so the town can solicit reliable bids before issuing bonds; members were told bids are expected by late fall with bond issuance and groundbreaking likely in the spring.
The motion passed unanimously; committee minutes were approved and staff will proceed with design work and bid procurement.