Commission declares necessity for 2027 Cape Seal special assessment district after residents press for full reconstruction on some streets
Summary
The commission declared necessity for the 2027 Cape Seal program, covering several unimproved streets with an estimated cost of $471,829. Residents of Fairview and Pleasant presented petitions asking that their streets be removed from cape sealing and scheduled for full reconstruction instead; the administration said petitions can delay or remove streets from the SAD.
Get email alerts on the Local Public Works topic
No spam. Unsubscribe anytime.
The Birmingham City Commission voted unanimously June 8 to declare necessity for the 2027 Cape Seal Special Assessment District, a city‑led program proposing cape‑seal treatment for multiple unimproved streets with an estimated project cost of $471,828.75.
Miss Cota of the engineering department described proposed streets in the northwest, southwest and south of downtown and explained the SAD model: 85% of front‑foot costs are assessed to properties fronting the improvement and 25% of side‑foot costs are assessed for residential properties. The staff estimated the cost per assessed front foot at $3,348.
At the public hearing, residents of Fairview and Pleasant submitted notarized petitions asking for full street reconstruction—curbs, gutters and sewer improvements—instead of cape seal. Tom Chisum of Fairview said the neighborhood had already voted in favor of a petition for new sewers and a reconstructed street and did not want to pay for a temporary cape seal that would be ripped up later.
Engineering staff said the petitions have been received and that the next steps are: (1) engineering will prepare a resident information packet and schedule a resident meeting with cost estimates, (2) if a petition remains above a 50% threshold the city will pursue design for a reconstructed street and (3) streets slated for full reconstruction will be removed from the cape seal contract or handled via alternate bidders. Staff warned scheduling is weather and bid dependent: some cape seal operations planned for August could be delayed into spring if heavy rains disrupt contractor schedules.
Commissioners asked staff to note in the record that estimated assessments could change if streets were removed from the SAD; the resolution adopted (with detailed assessment roles referenced to packet pages) set a confirmation hearing for June 22, 2026.
Action: The commission adopted the declaration of necessity and directed staff to prepare the assessment roll and notice for the confirmation hearing on June 22.