Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Development Fees topic
No spam. Unsubscribe anytime.
Los Fresnos delays some developer fees for Woods subdivision to ease force‑main cost
Summary
Council approved a combined approach (options two and three) to delay sidewalk installation and defer certain development and connection fees for the Woods subdivision to help the developer pay an unexpected roughly $1 million force‑main to the city sewer plant; council added a three‑year or phase‑two timetable for completion.
Get email alerts on the Development Fees topic
No spam. Unsubscribe anytime.
The council approved options intended to relieve early cash‑flow burdens on the Woods subdivision after staff explained the developer must run a long force main to the city sewer plant rather than tie into a nearby lift station. That change adds about $1 million to the developer’s phase‑one cost, staff said.
City staff offered four options and recommended against the city absorbing costs. The council settled on a combination of option two (delaying sidewalks to be installed when phase two is built) and option three (allowing certain development/connection fees to be paid on phase two) while setting a timetable — either by completion of phase two or within three years — so residents would not be left with indefinite delays.
Why it matters: The council’s action reduces upfront developer obligations temporarily to keep phase one financially viable and to move construction forward. Staff emphasized the delayed items remain required later; the council discussed including a firm timetable and possible enforcement provisions to ensure sidewalks and fees are provided.
Council approved the motion by voice/hand vote; the transcript records the outcome as “motion carries.”

